  • First phase of AH Laúca Transportation System concluded

    DATE: 10/31/2018

    Published by: OEC

    In October, the Laúca Hydroelectric Project commemorated the conclusion of the first phase of the Transportation System project associated with AH Laúca. The hydropower plant, which is the largest project of Odebrecht Engineering & Construction in Angola, accounts for 40% of all the power produced in the country’s North System.

    The project includes 305 km of 400 transmission lines installed and already in operation out of a total of 750 km to be delivered by 2020.

    This first phase included the lines Laúca-Capanda (40 km), Laúca-Cambutas (75 km) and lastly Laúca-Catete, for which a 190-km transmission line was built, which resulted in the expansion of Substation 400 kV in Catete.

    “The Laúca-Catete Transmission Line, which will improve the reliability of Angola’s power grid, will have the capacity to distribute the power produced by AH Laúca directly to the city of Luanda, thereby expanding the supply of electricity,” explained Leonardo Oikawa, manager of the project’s Transmission Lines.

    No comments

    Want to learn more
    about the subject?

    Click here and leave you suggestion
    for the next post

    Related news

    +
    0
    OEC

    Libro en formato digital que presenta una colección de artículos desarrollados en el programa OEC IN sobre tecnologías, retos...

    April 17, 2024
    +
    0
    OEC

    OEC – Engineering and Construction was voted one of the most innovative engineering companies of 2024 in the 5th edition...

    April 15, 2024
    +
    0

    We are pleased to inform you that the concessionaires H2Olmos and Trasvase Olmos have appointed Fernando Cilloniz Benavides and...

    March 27, 2024
    +
    0

    On Wednesday (27), the Brazilian Navy will launch the third conventional diesel-electric submarine built under the Submarine Development Program...

    March 27, 2024